| Project Name | Volume (Tons) | Year | Contractor | City |
|---|---|---|---|---|
| AL MUAJJIZ CRUDE OIL TERMINAL REHABILITATION | 500 | 2015 | EXTERRAN-BELELI ENERGY SRL | YANBU |
| COGENERATION INTERCONNECTION FACILITIES | 6,000 | 2015 | IMAD CO. | ABQAIQ / HAWIYAH |
| COGENERATION INTERCONNECTION FACILITIES | 4,000 | 2015 | FU-TAI ARABIA LLC | RASTANURA |
| RAMT | 1,000 | 2015 | JGC GULF | RASTANURA |
| INSTALLATION OF PIPELINE INSTRUMENT SCRAPPING FACILITIES | 1,000 | 2015 | GCC | ABQAIQ |
| NAPTHA & AROMATICS RP2 MECHANICAL WORK | 1,000 | 2014 | AL-RUSHAID CONST. CO., LTD. | YANBU |
| YANBU EXPORT REFINERY | 12,500 | 2012 | SKEC | YANBU |
| YANBU EXPORT REFINERY | 2,375 | 2012 | YANBU STEEL COMPANY | YANBU |
| JUBAIL EXPORT REFINERY | 1,875 | 2011 | M.R. AL KHATHLAN | JUBAIL |
| KARAN GAS FACILITIES PROJECT | 9,375 | 2011 | HYUNDAI ENG’G. & CONST. CO. | KHURSANIYAH |
| WASEA BULK PLANT | 2,875 | 2011 | SINOPEC INTERNATIONAL PETROLEUM | RIYADH |
| UBGT-1 SAUDI ARAMCO | 1,250 | 2011 | CAT | UTHMANIYA |
| SALES GAS FILTRATION SYSTEM | 2,500 | 2010 | AL ROBAYA CONTRACTING COMPANY | YANBU |
| KHURAIS CENTRAL PROCESSING FACILITIES | 11,250 | 2007 | HYUNDAI ENGG. & CONT. | KHURAIS |
| JUAYMAH GAS PLANT EXPANSION | 3,750 | 2007 | TECNICAS REUNIDAS | AL-JUAYMAH |
| KHURSANIYAH GAS PLANT | 2,500 | 2006 | BECHTEL & TECHNIP | KHURSANIYAH |
| BERRIE GAS PLANT | 6,250 | 2000 | AMEK BKW | JUBAIL |
| Volume (Tons) | Year | Contractor | Project Name |
|---|---|---|---|
| 2022 | Arabian Drilling | Tubulars requirement 2022 | |
| 5,388 | 2022 | NABORS ARABIA COMPANY LTD. | Tubulars requirement 2022 |
| 2,693 | 2022 | SAUDI ARAMCO NABORS DRILLING CO. | Tubulars requirement 2022 |
| 280 | 2022 | ITT SAUDI ARABIA | ITT Saudi Expansion |
| 198 | 2022 | TARGET CONSTRUCTION SAUDI COMPANY(W.L.L) | Upgrade Water Disposal Facility at Qatif (UDF) |
| 1,622 | 2022 | Nesma & Partners | Onshore Water Injection for Tanajib |
| 821 | 2022 | Saudi Aramco | ONSHORE & OFFSHORE MPP PROCUREMENT, UTHMANIYAH |
| 323 | 2022 | Saudi Aramco | STATIC EQUIP PURCHASING UNIT, JUAYMAH |
| 1,111 | 2022 | Domus Lloyd | SASREF : Jubail Rastanura Pipeline Project |
| 222 | 2022 | Saudi Archiridoon | UPGRADE FIRE WATER SYSTEM – RAS TANURA SOUTH TERMINAL |
| 1,111 | 2022 | Petronash | Gas Modular Skids |
| 667 | 2022 | Inma Steel | Gas Modular Skids |
| 2,889 | 2022 | SEPCO | KING SALMAN INTERNATIONAL COMPLEX FOR MARITIME INDUSTRIES AND SERVICES PROJECT |
| 222 | 2022 | NATIONAL CONTRACTING CO. LTD | REPLACE HIC AFFECTED PRESSURE VESSELS AT NGPD |
| 150 | 2022 | Wison Engineering Ltd. | Dew Point Control Facilities – Shaybah NGL |
| 3,556 | 2022 | Br. C.A.T. INTERNATIONAL CO. LIMITED | SOUTH GHAWAR UR – WELLS TIE-IN |
| 283 | 2022 | Br. C.A.T. INTERNATIONAL CO. LIMITED | South Ghawar (UR)-Transmission Pipelines |
| 573 | 2022 | McDermott Arabia Company Limited (MACL) | D7068 – Marjan Incremental Program – Package 1 Project |
| 901 | 2022 | SNAMPROGETTI SAUDI ARABIA | LTA For Offshore Facilities – Five (5) Jackets in MRJN & ABSF |
| 119 | 2021 | TARGET CONSTRUCTION SAUDI COMPANY(W.L.L) | REPLACE STORAGE TANK AT RAS TANURA REFINERY |
| 267 | 2021 | Nesma & Partners | Sulfur Handling Facility Jaladi Tanajib |
| 378 | 2021 | Nesma & Partners | South Ghawar Waterhandling Debottlenecking |
| 311 | 2021 | Nesma & Partners | Upgrade Abqaiq Water Injection |
| 1,021 | 2021 | Saudi Aramco | STATIC EQUIP PURCHASING UNIT, Shedgum |
| 222 | 2021 | Sendan International | Replace Water Chemical Injection System Abqaiq Plant |
| 444 | 2021 | Huta HegerFeld | Aramco Upgrade West Pier Facilities Rastanura |
| 222 | 2021 | Essar Projects | SHAYBAH CRUDE STABILIZATION ABQAIQ PLANT |
| 667 | 2021 | NESMA TATA PROJECTS | REPLACE GAS COMPRESSION – ABQAIQ PLANTS |
| 1,778 | 2021 | Kolin Insaat | South Dhahran Home Owner Ship Increment Project |
| 1,333 | 2021 | Petrojet | East An West Project |
| 2,222 | 2021 | EPPM – KSA Tunisian Saudi For Projects Co. Ltd. | PLANT AT UTHMANIYAH |
| 2,222 | 2021 | EPPM – KSA Tunisian Saudi For Projects Co. Ltd. | ARABIAN HEAVY DELIVERY TO YANBU EAST WESTPIPELINE |
| 222 | 2021 | ENPPI KSA | ARAMCO SAFANIYA 6 PROJECTS |
| 917 | 2021 | JGC Gulf Engineering Co. Ltd | South Ghawar Gas Separation Plant & Associated Facilities |
| 248 | 2020 | Saudi Aramco | STATIC EQUIP PURCHASING UNIT, UTHMANIYAH |
| 326 | 2020 | Saudi Aramco | STATIC EQUIP PURCHASING UNIT, JUAYMAH |
| 285 | 2020 | Saudi Aramco | ONSHORE & OFFSHORE MPP PROCUREMENT, SHEDGUM |
| 2,500 | 2017-2018 | HANWHA ENGINEERING CONSTRUCTION | JIZAN REFINERY & TERMICAL PROJ. PKG. 14 |
| 8,000 | 2017-2018 | DAYIM PUNJ LLOYD (AL-KHOBAR) | YASREF CLEAN FUEL INTERFACE FACILITIES |
| 8,000 | 2016-2018 | ARKAD ENGINEERING (AL-KHOBAR) | MASTER GAS PHASE II, PACKAGE 1 |
| 2,500 | 2016-2018 | ARKAD ENGINEERING (AL-KHOBAR) | MASTER GAS PHASE II, PACKAGE 1 |
| 3,500 | 2016-2018 | CONSOLIDATED CONTRACTING CO., (CCC) | JRTF-JSRU – JIZAN REFINERY & TERMINAL PROJECT |
| 5,000 | 2017-2018 | DENYS ARABIA -AL-KHOBAR | REPLACE THREE NORTHERN AREA PIPELINE -JUBAIL |
| 1,500 | 2016 | SAUDI ELECTRIC POWER CONST. CORP.(SEPCO) | MASTER GAS SYSTEM EXPANSION PROJECT – PHASE 1 |
| 500 | 2015 | EXTERRAN-BELELI ENERGY SRL | AL MUAJJIZ CRUDE OIL TERMINAL REHABILITATION |
| 6,000 | 2015 | IMAD CO. | COGENERATION INTERCONNECTION FACILITIES |
| 4,000 | 2015 | FU-TAI ARABIA LLC | COGENERATION INTERCONNECTION FACILITIES |
| 1,000 | 2015 | JGC GULF | RAMT PROJECT |
| 1,000 | 2015 | GCC | INSTALLATION OF PIPELINE INSTRUMENT SCRAPPING FACILITIES |
| 1,000 | 2014 | AL-RUSHAID CONST. CO., LTD. | NAPTHA & AROMATICS RP2 MECHANICAL WORK |
| Volume (Tons) | Year | Contractor | Project Name |
|---|---|---|---|
| 955 | 2022 | Petro Rabigh | BLANKET AGREEMENT, MAINTENANCE & SHUTDOWN |
| 600 | 2022 | Saudi Aramco Mobil Refinery Co Ltd (SAMREF) | BLANKET AGREEMENT, MAINTENANCE & SHUTDOWN |
| 850 | 2021 | SABIC | BLANKET AGREEMENT, MAINTENANCE & SHUTDOWN |
| 500 | 2020 | Saudi Aramco Jubail Refinery (SASREF) | BLANKET AGREEMENT, MAINTENANCE & SHUTDOWN |
| 4,500 | 2018-2019 | SAUDI ARAMCO REFINERY (SAMREF) | BLANKET AGREEMENT, MAINTENANCE & SHUTDOWN |
| 9,000 | 2015 | GSEC | PETRO-RABIGH II REFINING AND PETROCHEMICAL PROJECT (CP3 & 4) |
| 500 | 2014 | JACOBS ENGINEERING | SADARA PETROCHEMICAL COMPLEX – POLYETHYLENE TRAINS |
| 1,100 | 2014 | TECHNICAS REUNIDAS | SADARA PETROCHEMICAL COMPLEX – EOD / POD / EOSS PACKAGES |
| 1,166 | 2013 | CTCI | IBN RUSHD PET PLANT |
| 1,167 | 2013 | NATIONAL TITANIUM DIOXIDE (CRISTAL) | CRISTAL EXPANSION |
| 319 | 2013 | SAMSUNG | MA’ADEN ALUMINUM ROLLING MILL |
| Volume (Tons) | Year | Contractor | Project Name |
|---|---|---|---|
| 378 | 2022 | Yaqout Saudi Ceramic | Marafiq water and gas pipe line |
| 287 | 2022 | Al Fatah Water & Power | Phase 3 Expansion |
| 333 | 2022 | ALMOAYYED ELECTRICAL & INSTRUMENTATIONS | WATER TRANSMISSION FACILITY AT EAST HIDD |
| 222 | 2021 | PANORAMA CONTRACTING | WATER TRANSMISSION AL DUR IWPP -C 397 |
| 267 | 2021 | KARTEC W.L.L | NEW EXHIBITION AND CONVENTION CENTRE |
| 2,500 | 2020 | NESMA & PARTNERS | KAAR PROJECT |
| 2,000 | 2020 | MARAFIQ | POWER & WATER UTILITY FOR JUBAIL & YANBU |
| 2,500 | 2020 | MAADEN PHOSPHATE | WA’AD AL-SHAMAL PHOSPHATE COMPANY |
| 1,300 | 2020 | AIRMECH CONTRACTING | BAPCO MODERNIZATION |
| 1,000 | 2019-2020 | NASS MECHANICAL CONTRACTING | BAPCO MODERNIZATION |
| 4,000 | 2019 | SAIPEM Spa | WEST QURNA 1 PROJECT – MAJOR TIE-INS DS6 FACILITIES |
| 5,000 | 2018 – 2019 | SAUDI BINLADIN GROUP | AL-SHAMIYAH DEVELOPMENT |
| 550 | 2018 – 2019 | IKK | KING FAISAL SPECIALIST HOSPITAL |
| 500 | 2018 | EL-SEIF ENGINEERING | SHARMA ROYAL COMPLEX |
| 3,000 | 2018 | FEMCO | SFMC – HOSPITAL |
| 2,000 | 2018 | FEMCO | HOUSING & BUILDING – WADI AL HADA |
| 5,000 | 2017-2018 | SHAPOORJI PALLONJI | MEP-SABIC MAIN BUILDING |
| 2,000 | 2017 | NESMA & PARTNERS | SHARMA ROYAL COMPLEX |
| 2,000 | 2016 | WORLEY PARSON | FUEL GAS PIPELINE PP-13 |
| 3,000 | 2015-2017 | ASRY (BLANKET AGREEMENT) | REPAIRING SHIPYARD |
| 6,000 | 2015-2016 | BACS-RIYADH METRO | RIYADH METRO PROJECT |
| 3,000 | 2015-2016 | FAST – RIYADH METRO ALLIANCE | RIYADH METRO PROJECT |
| 10,000 | 2015 | SINOPEC SERVICES | SWCC YANBU-MADINAH PHASE-3 WATER TRANSMISSION SYSTEM PROJECT |
| 6,000 | 2015 | AZMEEL CONTRACTING | NFORMATION TECHNOLOGY AND COMMUNICATION COMPLEX (ITCC) |
| 15,000 | 2015 | SAUDI OGER/EL SEIF JV | HARAMAIN HIGH-SPEED RAIL NETWORK – JEDDAH & RABIGH (KAEC) STATIONS |
| 2,500 | 2014 | ASRY | REPAIRING SHIPYARD |
| 500 | 2014 | EL SEIF ENGINEERING & CONTRACTING | HAIL MALL: HAIL UNIVERSITY |
| 5,000 | 2014 | SAUDI BINLADIN GROUP | AL-SHAMIYAH DEVELOPMENT |
| 5,500 | 2014 | AL HAMMAM CO. | PP12 COMBINED CYCLE POWER PLANT |
| 3,750 | 2013 | PANORAMA | AL-DUR STORAGE TANK |
| 3,750 | 2013 | SAUDI BINLADIN GROUP | AL SHUMAISI EMERGENCY LODGING CENTER |